Guide

Set Up Teamwork for a Small Agency: A 2026 Build Guide

How to structure a Teamwork.com workspace for an agency of 5–15 people in 2026 — rate cards, retainers, budget burn-down and client access — with verified

· By Ace · Updated

Teamwork

Teamwork is the tool agencies reach for when they want to know whether a client is profitable before the invoice goes out, rather than at the accountant’s year-end surprise. It has native time tracking, project budgets, task billing methods and client users — the four things a generic project tool charges extra for or does not have.

It is also the tool most often bought and then run as a glorified task list, because the powerful parts are all in the setup decisions made in the first two weeks. An agency that imports a task list and starts logging time gets a timesheet. An agency that builds rate cards, budget thresholds and task-level billing methods before the first project gets a margin report.

This guide is the build order for an agency of 5–15 people starting from an empty account. It assumes you have bought or are about to buy; if you are still choosing, best PM software for agencies is where that decision belongs, and our Teamwork review covers what the platform is good and bad at. For a smaller business that is not agency-shaped, best PM software for small business is the better starting point.

TL;DR

  • Build in this order: rates → budget defaults → project template → client access → retainer projects → reporting. Doing it in any other order means reworking live projects.
  • Teamwork’s paid plans are Deliver at $13.99/month (or $10.99 billed yearly) and Grow at $25.99/month (or $19.99 billed yearly). The yearly prices quoted on the site are per user per month.
  • Get the client-users decision right before your first project. Client companies do not consume paid seats on the plans agencies buy, but they do consume setup work and they change how you structure visibility.
  • The seat-pricing trap in month two: agencies typically add a freelancer or a project manager in the middle of a project, discover the incremental cost, and then start sharing logins. Sharing logins destroys the time-tracking integrity the whole system rests on.
  • If you are under 8 people and not billing by the hour, Teamwork is over-specified. Use the pricing section below to check whether your retainer structure actually needs it.

What you should have at the end

Five states, and the workspace is done:

  1. Every person has a rate, and every project knows which rate to use.
  2. Every project is created from a template, with a budget set at creation rather than added later.
  3. Time entry is a weekly ritual with a named approver, not an end-of-month scramble.
  4. Clients can see what they need to see — progress and deliverables — without seeing internal notes, rates or other clients.
  5. One report per week answers: hours burned vs. budget, per client.

If your agency cannot produce item five on a Monday morning, it is paying for Teamwork and using a task board.

Prerequisites: three decisions before you build

The structure below mirrors what a well-run agency already does on paper; the tool only removes the manual assembly. If your client relationships are more like consulting engagements than agency deliveries, set up Asana for consultants and best PM software for consulting firms describe a different build.

Decision 1 — the billing model per client type. Teamwork supports fixed-fee, time-and-materials, non-billable and retainer projects. Agencies usually run all four: project work at fixed fee, ongoing support on a monthly retainer, pitch work non-billable, and change requests at T&M. Decide which of your client relationships fit which model before you create projects, because the model determines the budget method at creation and it is painful to convert a live project.

Decision 2 — the rate ladder. Set rates on roles, not on individuals. A three-tier ladder (Director / Senior / Junior) with a blended rate per tier gives you a defensible budget without gossiping about salaries inside the tool. Individual overrides exist, use them for contractors only.

Decision 3 — who owns the weekly time review. This is an organisational decision with a tooling consequence: the person who chases timesheets needs the Approver permission and the standing agenda slot. Agencies where nobody owns this end up with 40% of time entries landing in the last working day of the month, which makes the budget burn-down chart a work of fiction for the other 27 days.

Step 1 — Set up the account, currency and fiscal year

Create the account and set the currency before anything else. Multi-currency agencies should set the company currency to the one they invoice in most, not the one the bank account is in, because budget reporting reads in company currency.

Set the fiscal year start explicitly if your agency does not run on a calendar year. This affects every “year to date” figure on the dashboard, and retrofitting it is a support ticket.

If you are comparative-shopping instead of building, the client-delivery tools that compete with Teamwork is covered by our Rocketlane review, and Set Up Rocketlane for Agencies is the equivalent build guide for the onboarding-heavy end of the market.

Step 2 — Build the rate card before you build a project

Go to the rate settings and create the three-tier ladder. Two things to get right:

Billable rate vs. cost rate. Teamwork can hold both. If you only enter the billable rate, your profitability report shows revenue but not margin, because there is no cost side. Enter both for employees, billable only for contractors whose cost is their billable rate.

Default rate per role, not per person. Set the role default, then override individuals only where the rate genuinely differs. When you promote a junior to senior next year you change the role, and every future project picks up the right rate without a project-by-project edit.

If you skip this step and start logging time, you will eventually have three months of time against the wrong rate and a budget report nobody trusts. The same rate-first discipline appears in setting up Kantata for a consulting firm, where rates attach to roles for the same reason.

The same discipline applies on the delivery side: asana workflow for agencies walks through the equivalent structure if you are comparing how a non-financial tool would model it, and it is a useful sanity check on whether your agency’s actual workflow is agency-shaped or just busy.

Step 3 — Set agency-level budget defaults

Before the first project, set the defaults that every project inherits:

  • Budget type. Hours-based, fee-based, or both. Agencies that bill by retainer should default to both — hours for operational control, fee for financial control.
  • Budget threshold alerts. Set an alert at 75% and 90% of budget. This is the highest-return setting in the entire workspace: it turns the budget from a post-mortem into an early warning.
  • Default task billing method. Fixed fee tasks will silently overrun if the budget is calculated by hours. Decide per project type and document the decision, because the default is applied at project creation and changing it later only affects new tasks.

Step 4 — Build the project template (this is the real work)

The template is where an agency’s discipline lives or dies. Build one template per project type — typically three: a fixed-fee project, a retainer month, and a pitch.

For the fixed-fee project template:

  1. Phase structure: Discovery → Design → Build/Production → Review → Delivery → Post-launch. Use the agency’s own vocabulary; templates written in consultants’ language get ignored.
  2. Task-level estimates at the smallest unit of work you can estimate honestly. Estimates are what the budget consumes; a task with no estimate is invisible to the budget engine.
  3. A “Change request” task category with its own budget line, so scope creep is visible as a category rather than absorbed silently into overruns. This is the single most useful structural decision for agency profitability, and it pairs with the client reporting workflow you will run monthly.
  4. Billable default set on the categories that are billable, non-billable on internal review and admin. Getting this wrong inflates your billable utilisation, which flatters the report and misleads the pricing decision.
  5. A milestone per client-facing deliverable, with the approval dependency on the client. That dependency is what makes the “we are late because they did not sign off” conversation possible with evidence.

For the retainer template: one project per client per month, or one project with a repeating month-long milestone. The first is easier to report on and easier to close cleanly; the second avoids project sprawl. Agencies under 10 people should use one project per client with a monthly milestone, which keeps the project list navigable. Design-led studios should also read best PM software for design agencies before locking the template — the template shape changes when the deliverable is a review cycle rather than a build.

Step 5 — Set up client users correctly the first time

Agencies get this wrong in a way that either leaks internal information or buries the account manager in screenshots.

Two tiers of external access:

  • Client company users see projects shared with them, comment on tasks they are involved in, and can view files. They are the right level for a day-to-day client contact.
  • Client “view only” access should be the default for stakeholders who want a progress view and nothing else.

What must be off by default: time entries at the rate level, internal task comments, and any project not explicitly shared. Check the visibility defaults before inviting the first client, because an accidental rate disclosure is not recoverable — the client has seen your margin.

Who gets an invite: the client’s project lead and one backup. Inviting a whole client team creates a support burden and gives you six people with partial context. For a deeper look at the client-facing layer, client onboarding workflow in a PM tool covers the sequencing.

Step 6 — Run the weekly ritual that makes the system true

A configured Teamwork workspace is only accurate if time arrives weekly. Set this up in week one:

  • Monday 10:00 — timesheet reminder to all staff, due by end of Tuesday.
  • Tuesday — approver reviews and rejects entries without a project or task.
  • Wednesday — one report to the leadership team: hours burned vs. budget per client, with the two clients closest to their threshold named explicitly.

That Wednesday report is the smallest possible version of the profitability loop, and it is what stops an agency discovering in month three that a retainer has been running at 130% of budget since month one.

Pricing: what Teamwork actually costs a small agency in 2026

Plan Price per user/month (billed yearly) Price per user/month (billed monthly) What it gives you
Free $0 $0 Basic project and task management for teams getting started
Deliver $10.99 $13.99 Core project management with time tracking
Grow $19.99 $25.99 Advanced automation and reporting, described by Teamwork as for agencies
Scale Quoted per business Quoted per business Workflow scale, listed as 100,000 automations
Optimize Quoted per business Not published Enterprise-grade security and control

Verified against Teamwork’s official pricing page on 2026-11-12.

Three things in that table matter more than the headline number.

The yearly prices are per user per month, not per year. Teamwork’s pricing page presents the plans inside the comparison table at $9.99, $24.99 per user/month billed yearly, while the structured offer data on the same page lists Deliver at $10.99 (annual) / $13.99 (monthly) and Grow at $19.99 (annual) / $25.99 (monthly). Those are not contradictory tiers — the page was mid-refresh when we checked it, showing legacy plan names (Basics / Accelerate) in the comparison table alongside the current names (Deliver / Grow) in the offer data. Ask the sales team to confirm which plan name your account will be provisioned as, and get the rate in writing, because budgeting $9.99 and being invoiced $10.99 is a 10% miss on the software line.

Scale and Optimize have no public price. Teamwork lists both as “Let’s talk” / quoted per business. Do not build a budget from a figure you read elsewhere; an agency with 12 seats on Grow is at $2,878.56 per year (12 × $19.99 × 12), and that is knowable. The tier above is not.

The seat cost compounds with headcount, not with billable hours. A 10-person agency on Grow pays $2,398.80/year. Adding two freelancers for a busy quarter is another $479.76/year if you give them seats — which is why agencies start sharing logins, and why shared logins are the most expensive “saving” in this whole build, because they make the time data worthless and the margin report unfalsifiable.

The decisions that actually matter for a small agency

If your team is under 8 people and most of your work is fixed-fee projects, Deliver at $10.99 is enough. Grow’s automation and reporting add value when you have enough projects that manual status updates cost more than the $9/user/month delta — as a rule of thumb, that threshold arrives around six concurrent clients with at least one project each.

If you run retainers, Grow pays for itself the first month it catches a retainer at 110% of budget. The reporting layer is the product for a retainer business; Deliver will track the hours but make you assemble the client-facing story by hand.

If you bill by the hour and your clients audit invoices, do not give clients a login at all. Export the time report and send a PDF. Client access is a relationship feature, and a client who can see raw time entries will audit them, which converts a professional relationship into a billing dispute about whether a 12-minute entry was a phone call or a task. Agencies running under 15 people are usually better served by the client reporting workflow pattern than by live access.

If you have contractors, give them seats but restrict them to assigned projects. A contractor with workspace-wide visibility sees every client’s name, which is a confidentiality problem the day they take a competing brief.

Where Teamwork will not save you

Two structural limits worth knowing before you build:

The tool cannot fix an estimating culture. If your team estimates optimistically and the budget is built from those estimates, every project runs at 120%. Teamwork will show you the overrun earlier than a spreadsheet, which is valuable, but the fix is a retrospective habit: after each project, compare estimated to actual by task category and adjust the template. An agency that does not do this will conclude, wrongly, that the tool does not work.

Reporting breadth has limits at the lower tiers. Cross-project dashboards and the deeper profitability views are where the plan tier bites. If your leadership team’s primary need is a single screen showing margin by client across 20 projects, check the reporting capability on the tier you are buying in a trial before you commit — the trial is free and the cost of discovering a gap after rollout is a year of manual exports.

A 30-day rollout plan

Week 1 — Account, currency, fiscal year. Rate ladder (three tiers, billable + cost). Budget alert thresholds at 75/90%.

Week 2 — One project template, for your most common project type. Built with the person who actually delivers the work, not by management alone. Do not build all three templates yet.

Week 3 — Run one real project on the template with real time entry, weekly reminder, named approver. Do not invite clients yet.

Week 4 — Review: did the budget alert fire usefully? Were the estimates honest compared to actuals? Adjust the template. Then invite the first client and build the second template.

Agencies that try to build all three templates and onboard all clients in week one end up with three half-configured templates and no weekly ritual. Sequenced properly, the workspace is stable by day 30 and the second and third templates take an afternoon each.


Methodology and disclosure. Plan names and prices were read from Teamwork’s official pricing page on 2026-11-12, including the structured offer data embedded on that page; the discrepancy between the comparison table’s legacy plan names and the current Deliver/Grow offer data is reported as found rather than resolved, and readers should confirm their provisioned plan and rate with Teamwork before budgeting. We do not claim to have independently tested Teamwork on a live agency account; the build order and the team-size judgements are derived from the documented feature set, published pricing structure and common agency operating patterns, not from a measured deployment. Any figures in the rollout plan are illustrative arithmetic from the published per-seat price, not quotes.